Installation of electrical panels for the water pumping station of the Municipality of Dionysos

Services Installation

ARPEDON undertook the design, supply and installation of the new electrical panels for the water pumping station of the Municipality of Dionysos.

The pumping station houses 3 pumping units with different energy requirements.

The new electrical panel is a 4 field with 1 Inverter for pumping unit 140 kW and 2 Inverters for pumping units 75 kW.

Prior to the connection of the panels, the dielectric strength of the cables was checked and all the necessary checks were performed to ensure correct and safe execution.

The power outage of the pumping station was less than 3 hours in total.

For the delivery of the project, field tests were performed in all panels according to the standard EN 61439 by an accredited body (LABOR SA) where the results showed complete compliance.

Subscribe to the newsletter

Occasional emails with useful information on industry and maintenance.

blog
25.10.2026

Operating-Mode Baselines for Vibration Alarming on Variable-Load/Speed Machinery

Maintenance Mechbase Condition Based Maintenance
blog
19.05.2026

Ten Dangerous Noises in an Electrical Substation

Services Maintenance

Tell us about your project

Send us the drawings and the project dates.